← All schemes

Other Specified Works

Central Sector SchemeMinistry of Railways

Budget 2026-27
₹1,371 crore
Actually spent, 2024-25
₹1,151 crore
−5.9% vs budget of ₹1,222 crore

Allocation and spending

Outcome (actual, or revised where actuals aren't out yet) and the amount announced in each budget.

  • Outcome
  • Announced in the budget
  • Estimate (no actual yet)
0 Cr500 Cr1K Cr2K Cr2017-182020-212023-242026-270 Cr500 Cr1K Cr2K Cr2016-172018-192020-212022-232024-252026-27
Show as table
YearOutcomeAnnounced in the budget
2015-16₹353.83 crore–
2016-17₹263.30 crore–
2017-18₹210.91 crore₹395.05 crore (BE)
2018-19₹288.43 crore₹660 crore (BE)
2019-20₹455.83 crore₹970 crore (BE)
2020-21₹119.71 crore₹875 crore (BE)
2021-22₹543.02 crore₹775 crore (BE)
2022-23₹556.22 crore₹740 crore (BE)
2023-24₹794.60 crore₹1,300 crore (BE)
2024-25₹1,150.68 crore₹1,222.26 crore (BE)
2025-26₹1,370.62 crore (RE)₹1,241 crore (BE)
2026-27–₹1,370.77 crore (BE)

Expenditure Profile Statement 4B, Budgets 2017-18 to 2026-27.

Every figure

Each figure links to the official PDF it was read from. Budget Estimates come from that year's budget, Revised Estimates from the next, Actuals from the one after.