Budget 2026-27
₹1,952 crore
Actually spent, 2024-25
₹1,596 crore
−5.1% vs budget of ₹1,682 crore

Allocation and spending

Outcome (actual, or revised where actuals aren't out yet) and the amount announced in each budget.

  • Outcome
  • Announced in the budget
  • Estimate (no actual yet)
0 Cr500 Cr1K Cr2K Cr2K Cr2017-182020-212023-242026-270 Cr500 Cr1K Cr2K Cr2K Cr2016-172018-192020-212022-232024-252026-27
Show as table
YearOutcomeAnnounced in the budget
2015-16₹105.94 crore–
2016-17₹140.38 crore–
2017-18₹166.37 crore₹361.61 crore (BE)
2018-19₹249.94 crore₹220 crore (BE)
2019-20₹482.86 crore₹915 crore (BE)
2020-21₹71.39 crore₹780 crore (BE)
2021-22₹628.21 crore₹850 crore (BE)
2022-23₹734.96 crore₹650 crore (BE)
2023-24₹1,434.41 crore₹1,650 crore (BE)
2024-25₹1,596.41 crore₹1,681.87 crore (BE)
2025-26₹1,958.83 crore (RE)₹1,650.50 crore (BE)
2026-27–₹1,952.27 crore (BE)

Expenditure Profile Statement 4B, Budgets 2017-18 to 2026-27.