Integrated Scheme for Skill Development
Central Sector SchemeMinistry of Textiles
Budget 2026-27
₹300 crore
Actually spent, 2024-25
₹259 crore
+56.0% vs budget of ₹166 crore
Allocation and spending
Outcome (actual, or revised where actuals aren't out yet) and the amount announced in each budget.
- Outcome
- Announced in the budget
- Estimate (no actual yet)
Show as table
| Year | Outcome | Announced in the budget |
|---|---|---|
| 2015-16 | ₹134.27 crore | – |
| 2016-17 | ₹250.79 crore | – |
| 2017-18 | ₹100 crore | ₹173.99 crore (BE) |
| 2018-19 | ₹18.39 crore | ₹200 crore (BE) |
| 2019-20 | ₹72.07 crore | ₹100.50 crore (BE) |
| 2020-21 | ₹80 crore (RE) | ₹150 crore (BE) |
| 2021-22 | ₹59.76 crore | ₹100 crore (BE) |
| 2022-23 | ₹23.27 crore | ₹100 crore (BE) |
| 2023-24 | ₹114.99 crore | ₹115 crore (BE) |
| 2024-25 | ₹258.94 crore | ₹166 crore (BE) |
| 2025-26 | ₹260 crore (RE) | ₹330 crore (BE) |
| 2026-27 | – | ₹299.96 crore (BE) |
Expenditure Profile Statement 4B, Budgets 2017-18 to 2026-27.
Every figure
| Year | Budget Estimate | Revised Estimate | Actual |
|---|---|---|---|
| 2015-16 | – | – | ₹134.27 crore |
| 2016-17 | – | ₹221.90 crore | ₹250.79 crore |
| 2017-18 | ₹173.99 crore | ₹100 crore | ₹100 crore |
| 2018-19 | ₹200 crore | ₹42 crore | ₹18.39 crore |
| 2019-20 | ₹100.50 crore | ₹100.50 crore | ₹72.07 crore |
| 2020-21 | ₹150 crore | ₹80 crore | – |
| 2021-22 | ₹100 crore | ₹90 crore | ₹59.76 crore |
| 2022-23 | ₹100 crore | ₹25 crore | ₹23.27 crore |
| 2023-24 | ₹115 crore | ₹115 crore | ₹114.99 crore |
| 2024-25 | ₹166 crore | ₹331 crore | ₹258.94 crore |
| 2025-26 | ₹330 crore | ₹260 crore | – |
| 2026-27 | ₹299.96 crore | – | – |
Each figure links to the official PDF it was read from. Budget Estimates come from that year's budget, Revised Estimates from the next, Actuals from the one after.