Electrification Projects

Central Sector SchemeMinistry of Railways

Budget 2026-27
₹5,000 crore
Actually spent, 2024-25
₹4,248 crore
−34.4% vs budget of ₹6,472 crore

Allocation and spending

Outcome (actual, or revised where actuals aren't out yet) and the amount announced in each budget.

  • Outcome
  • Announced in the budget
  • Estimate (no actual yet)
−3K Cr0 Cr3K Cr5K Cr8K Cr10K Cr2017-182020-212023-242026-27−3K Cr0 Cr3K Cr5K Cr8K Cr10K Cr2016-172018-192020-212022-232024-252026-27
Show as table
YearOutcomeAnnounced in the budget
2015-16₹14.75 crore–
2016-17₹10.64 crore–
2017-18−₹2.79 crore₹10 crore (BE)
2018-19−₹5.79 crore₹2 crore (BE)
2019-20₹0.95 crore₹1 crore (BE)
2020-21₹1.21 crore₹1 crore (BE)
2021-22₹0.37 crore₹10 crore (BE)
2022-23₹340.14 crore–
2023-24₹5,806.98 crore₹8,070 crore (BE)
2024-25₹4,248.38 crore₹6,472.30 crore (BE)
2025-26₹4,500 crore (RE)₹6,150 crore (BE)
2026-27–₹5,000 crore (BE)

Expenditure Profile Statement 4B, Budgets 2017-18 to 2026-27.

Every figure

Each figure links to the official PDF it was read from. Budget Estimates come from that year's budget, Revised Estimates from the next, Actuals from the one after.